Karachi Building Collapse: Death Toll Reaches 13 as City Seals 516 Illegal Buildings


The death toll from the collapse of a six-storey building in Karachi has risen to 13, with four people still missing, as rescue teams work around the clock and the Sindh government moves against hundreds of illegal buildings across the city.

The building, under construction in the Administration Employees Housing Society (KAECHS) near Baloch Colony, collapsed at around 1 p.m. on Wednesday 25 November 2026. Three people were killed on the spot and 14 others were injured. Since then, rescuers have pulled body after body from the rubble — and one man alive, after 54 hours buried under concrete.

Four Days of Rescue

The search went on for four days. Another body was recovered on Thursday, taking the death toll to four. On Friday, four more bodies were recovered, taking the toll to eight. On Saturday, rescue workers recovered four more bodies — one at around 4:20 a.m., two more around 8:30 a.m. and a fourth in the afternoon — and located a 13th body in the debris, with efforts under way to retrieve it. Four people remain unaccounted for.

Rescue 1122 spokesperson Hassaanul Haseeb Khan said teams had moved to "fast track" operations from all four sides of the wreckage and hoped to finish on Saturday night. Videos from the site showed members of the Urban Search and Rescue team using heavy-duty bolt cutters to cut through reinforcing bars while clearing rubble with machinery. Rescuers razed a wall of a vacant plot next to the site to create an entry route, and heavy machinery was brought in to clear the debris.

"The operation will continue until the recovery of everyone from the rubble," Khan said.

A total of 15 people have been rescued alive since the collapse. Among them was Muhammad Adil, a 28-year-old marble worker from Golimar, who was pulled from the debris on Friday after remaining trapped beneath the collapsed structure for more than 50 hours. Sindh Chief Minister Murad Ali Shah described his survival as a "miracle" and directed rescue agencies and the Karachi commissioner to accelerate the operation and deploy all available resources. Adil told rescuers that two other people who might be alive were in touch with him.

A Building That Should Never Have Been Six Storeys

The building was reportedly being constructed illegally on a residential plot. It had been approved in March 2026 for a basement, a ground floor and one additional storey on a 600-square-yard plot — yet it rose to six storeys before it came down.

That single fact is at the heart of the tragedy. Karachi, Pakistan's largest city and commercial hub, has a long history of unauthorised construction and weak enforcement of building regulations. Buildings are routinely built higher than approved, on plots meant for houses, with poor materials and no proper engineering. When they collapse, the workers inside — often daily-wage labourers with no safety protection — pay the price.

A first information report (FIR) was registered at the Tipu Sultan police station on Wednesday, on the complaint of an official of the Sindh Local Government Department. The FIR invoked sections including 302 (intentional murder) and 119 (public servant concealing design to commit an offence). The chief minister directed police to immediately arrest the building's owner, Salman Tahir, and the builder, Zeeshan.

Action Against Illegal Buildings

The collapse has triggered the biggest crackdown on illegal construction in Karachi in years. On the orders of the chief minister, the city administration has taken action against as many as 516 buildings since the collapse, the Karachi Commissioner's Office reported to the chief minister on 27 November. Action was taken against 262 buildings under construction in various districts, and the rest were sealed or marked for demolition.

On Thursday, Chief Minister Murad Ali Shah ordered the removal of senior officials, including Waseem Shamshad, who served as both Sindh Building Control Authority (SBCA) director general and local government secretary, and the suspension of 16 SBCA officers following the collapse.

The SBCA is the body responsible for approving building plans and checking that construction follows them. The suspensions suggest the government believes its own officers either looked the other way or were part of the system that allowed an illegal six-storey building to rise in a residential neighbourhood.

A Familiar Pattern

Karachi has seen building collapses before, and each time the same questions are asked: who approved it, who inspected it, and who was paid to ignore it? In 2020, a five-storey building collapsed in the city's Gulbahar area, killing at least 27 people. In other cases, buildings have been evacuated just in time, or have stood for years as dangerous structures while residents lived inside them, unaware of the risk.

The problem is not a lack of rules. Karachi has building regulations, approval processes and a control authority. The problem is enforcement — and the money to be made by ignoring it. A residential plot can earn far more as a multi-storey building, and the difference between one approved floor and six illegal ones is worth a fortune to a builder. When the system that is supposed to stop that is weak or corrupt, the result is measured in lives.

Builders, meanwhile, have pushed back against the crackdown, threatening a shutdown and claiming action is being taken against officially approved projects as well. That tension — between a government under pressure to act and an industry that says it is being treated unfairly — will shape what happens next.

What Needs to Change

Experts say the collapse shows the need for three things. First, real inspections during construction, not just paper approvals. A building that is approved for two storeys cannot become six without someone noticing — unless nobody is looking. Second, accountability that reaches beyond the builder to the officials who allowed it. The suspension of 16 officers is a start, but prosecutions and convictions are what change behaviour. Third, protection for the workers and residents who live and work in these buildings, including proper safety equipment on construction sites and clear warnings when a building is unsafe.

For the families of the dead, those reforms will come too late. The victims identified so far include young men in their twenties and thirties — labourers and workers with names like Muhammad Naveed, Farhan, Muhammad Arsalan, Abid, Bilal, Muhammad Ali, Sagheer, Haseeb, Waqas and Jibran — most of them earning a daily wage on a building site. Four more families are still waiting to know whether their loved ones are among the missing.

The rescue operation is expected to finish soon. The crackdown on illegal buildings will continue. But Karachi has been here before, and the real test is not how many buildings are sealed this week — it is whether, a year from now, another illegal building is still rising, floor by floor, over a residential street, with nobody stopping it.